Overall Progress
72%
18
Total Items
13
Done
4
In Progress
1
Pending
Milestones
Discovery & Architecture
Completed · Feb 28
Design System v1
Completed · Mar 15
Backend Integration
In Progress · Due Jun 15
Final QA & Launch
Pending · Due Jun 30
Scope Items
| # | Scope Item | Category | Assigned | Status | Progress | Est. Hrs | Actual | Due | |
|---|---|---|---|---|---|---|---|---|---|
|
Frontend Development
6 items
Est: 120h · Done: 86h
|
|||||||||
| FE-01 | Design System Implementation Tailwind v4, tokens, component library |
Frontend | JS |
Done | 100% |
32h | 29h | Mar 15 | |
| FE-01.1 | Color tokens & typography system | JS |
Done | 8h | 7h | Mar 5 | |||
| FE-01.2 | 220 component library (buttons, forms, nav) | JS |
Done | 24h | 22h | Mar 15 | |||
| FE-02 | Authentication Flow Login, register, 2FA, password reset |
Frontend | JS |
Done | 100% |
20h | 18h | Apr 1 | |
| FE-03 | Dashboard & Analytics UI Charts, KPIs, real-time data tables |
Frontend | JS |
In Progress | 65% |
28h | 18h | Jun 20 | |
|
Backend & API
5 items
Est: 90h · Done: 60h
|
|||||||||
| BE-01 | REST API Architecture Node.js, Express, JWT auth middleware |
Backend | MK |
Done | 100% |
35h | 32h | Apr 15 | |
| BE-02 | GraphQL Gateway Apollo Server, schema stitching, subscriptions |
Backend | MK |
In Progress | 70% |
30h | 21h | Jun 25 | |
| BE-03 | Database Design & Migration PostgreSQL, Prisma ORM, seed data |
Backend | MK |
Done | 100% |
25h | 28h | Apr 30 | |
|
UI / UX Design
4 items
Est: 48h · Done: 48h
|
|||||||||
| DS-01 | Wireframes & User Flows Figma wireframes, user journey mapping |
Design | PR |
Done | 100% |
16h | 14h | Feb 28 | |
| DS-02 | High-Fidelity Mockups All screens, responsive variants, dark mode |
Design | PR |
Done | 100% |
32h | 34h | Mar 20 | |
|
QA & Deployment
3 items
Est: 24h · Done: 0h
|
|||||||||
| QA-01 | End-to-End Testing Playwright, CI suite, 90% coverage |
QA | SA |
Pending | 0% |
16h | — | Jun 28 | |
| QA-02 | Performance Optimisation Lighthouse ≥95, bundle analysis, caching |
QA | SA |
Pending | 0% |
8h | — | Jun 29 | |
| QA-03 | Production Deployment Vercel / AWS, env config, DNS setup |
QA | JS |
Pending | 0% |
— | — | Jun 30 | |